Expediting Cost Question

9:25 PM 01/11/2013

 

Expediting Cost question: looking for some preliminary budget numbers for following:
Alt1 filing, DOB, LPC filing, amended CoO, probably zoning study to confirm feasability of added space also, scope is adding appox 200sf to existing terrace on duplex PH,
any insight much appreciated!

 

 

3 answers
  • vote

    $ 8.000 - $ 15.000

    7:58 AM 01/12/2013 | 0 Votes

     

     

  • vote

    $8,000 for the Alt 1 filing.  Pulling permits and sign-off are usually additional.  Zoning analysis somewhere between $800 - $1,500.
    Ula Bochinska, Bostudio Architecture, www.bostudio.us

    8:47 PM 01/12/2013 | 0 Votes

     

     

  • vote

    8000-15000 would include C of O if it's for strictly expediting. There are additional costs such as architect/engineer, reports, inspections, surveyor, DOB fees, etc.

    1:18 PM 01/14/2013 | 0 Votes

     

     

Answer